Tangipahoa Parish plans much road work this week

Posted: Monday, August 24, 2020 | Views: 536

Tangipahoa Parish plans much road work this week


HAMMOND—Tangipahoa Parish President Robby Miller said the parish’s overlay work has reached the punch list phase, with dressing work and finishing touches planned this week, weather permitting.

Miller said the parish contractor has scheduled the following streets for dressing work during the week of August 24:

*On Monday, August 24, crews will dress Pleasant Ridge, N. 7th Street, and Barringer Drive;

*On Tuesday, August 25, crews will dress N. 7th Street, Barringer Drive, Pleasant Ridge, and Professional Plaza;

*On Wednesday, August 26, dressing work continues on Professional Plaza, Brandon Court, and Brandon Drive;

*On Thursday, August 27, the contractor will dress Brandon Court, Brandon Drive, Vinyard Trace, Muscarello, and Watson;

*On Friday, August 28, dressing crews will continue work on Watson, Arena, Ogden, and BT Thomas.

Miller said punch list items will also be addressed daily, as weather permits.

All work will be posted on the day of construction.